dc.identifier.citationD. Curto, F. Acebes, J.M. González-Varona, D. Poza, Impact of aleatoric, stochastic and epistemic uncertainties on project cost contingency reserves, International Journal of Production Economics, Volume 253, 2022, 108626, ISSN 0925-5273, https://doi.org/10.1016/j.ijpe.2022.108626.es_ES
dc.identifier.urihttps://hdl.handle.net/10630/33470
dc.description.abstractIn construction projects, contingency reserves have traditionally been estimated based on a percentage of the total project cost, which is arbitrary and, thus, unreliable in practical cases. Monte Carlo simulation provides a more reliable estimation. However, works on this topic have focused exclusively on the effects of aleatoric uncertainty, but ignored the impacts of other uncertainty types. In this paper, we present a method to quantitatively determine project cost contingency reserves based on Monte Carlo Simulation that considers the impact of not only aleatoric uncertainty, but also of the effects of other uncertainty kinds (stochastic, epistemic) on the total project cost. The proposed method has been validated with a real-case construction project in Spain. The obtained results demonstrate that the approach will be helpful for construction Project Managers because the obtained cost contingency reserves are consistent with the actual uncertainty type that affects the risks identified in their projects.es_ES
dc.description.sponsorshipThis research has been partially financed by the Regional Government of Castilla and Leon (Spain) with Grant (VA180P20)es_ES
dc.language.isoenges_ES
dc.publisherELSEVIER (International Journal of Production Economics)es_ES
dc.rightsinfo:eu-repo/semantics/openAccesses_ES
dc.rights.urihttp://creativecommons.org/licenses/by-nc-nd/4.0/*
dc.subjectMontecarlo, Método dees_ES
dc.subjectIncertidumbrees_ES
dc.subject.otherCost contingencyes_ES
dc.subject.otherMonte Carlo simulationes_ES
dc.subject.otherUncertaintyes_ES
dc.subject.otherIntegrated risk managementes_ES
dc.titleImpact of aleatoric, stochastic and epistemic uncertainties on project cost contingency reserveses_ES
dc.typeinfo:eu-repo/semantics/articlees_ES
dc.centroEscuela de Ingenierías Industrialeses_ES
dc.identifier.doi10.1016/j.ijpe.2022.108626
dc.rights.ccAttribution-NonCommercial-NoDerivatives 4.0 Internacional*
dc.type.hasVersioninfo:eu-repo/semantics/publishedVersiones_ES


Ficheros en el ítem

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

Attribution-NonCommercial-NoDerivatives 4.0 Internacional
Excepto si se señala otra cosa, la licencia del ítem se describe como Attribution-NonCommercial-NoDerivatives 4.0 Internacional